Dubai off-plan payment plans explained
A Dubai off-plan payment plan splits the price into a booking deposit, instalments during construction and a balance at handover. The two numbers in a plan such as 60/40 tell you how much is due before handover and how much on completion. The plan changes when you pay, not what the property is worth.
How to read the numbers
Developers describe plans as a ratio. In a 60/40 plan you pay 60% of the price while the building is under construction and the remaining 40% when it is handed over. A 70/30 or 80/20 plan asks for more during the build and leaves a smaller balance at the end. A 50/50 plan feels lighter during construction but leaves a bigger payment on completion.
Most plans start with a booking deposit, commonly somewhere between 5% and 20% of the price, followed by instalments that are either tied to construction milestones or fall on fixed dates.
The three structures you will be offered
| Structure | How it works | Suits |
|---|---|---|
| Construction-linked | Instalments fall due as the build reaches set stages, with the balance at handover. | Buyers who want payments to follow real progress on site. |
| Time-linked | Instalments fall on fixed dates, for example every three or four months, whatever stage the build has reached. | Buyers who want certainty over dates for budgeting. |
| Post-handover | Part of the price is paid after you receive the keys, usually over one to five years. | Investors who want rent to overlap with the last instalments. |
Through 2026, larger developers have been moving away from long post-handover terms and towards construction-linked plans such as 70/30 and 80/20. If a plan looks unusually generous, ask why.
A worked example
Take an apartment priced at AED 1,500,000 on a 60/40 plan.
| Stage | Amount |
|---|---|
| Paid during construction (60%) | AED 900,000 |
| Paid at handover (40%) | AED 600,000 |
| Dubai Land Department registration fee (4%), paid near the start | AED 60,000 |
The 4% fee is the detail UK buyers most often miss. On an off-plan purchase it is paid when the contract is registered, close to the beginning, so it sits on top of your first instalments. There is no second 4% at handover. The full list of fees is in the cost of buying property in Dubai.
Plan for the handover payment before you book
The handover balance is usually the largest single payment. You have three ways to meet it: cash, a mortgage arranged close to completion, or selling the unit before handover if the contract allows it. Each needs checking early.
- Mortgage: bank lending on an unfinished property is capped at 50% of its value, and approval depends on the developer, the project and your own profile. See mortgages for UK residents.
- Resale before handover: many developers only allow this once a set share of the price has been paid. The percentage is in the sale contract, so read it before relying on an early exit.
- Cash: the dirham is pegged to the US dollar, so the pound cost of a payment due in two years will move with the pound-dollar rate.
Handover dates move
Build your plan around the possibility of delay. The supply analysis in my playbook, which covers nearly two decades of Dubai completions, found that 44% of projects with a stated completion date landed on schedule and 47% ran late, by a median of 14 months. A delay pushes back your rental income, and on a time-linked plan your instalments carry on regardless.
What I look at before the plan
A payment plan is a way of paying. It tells you nothing about whether the price is right. An overly attractive plan can sit on top of an inflated price or a weaker location, and when the market softens it can hold you in place. Start with the developer's delivery record, the location and who will rent or buy the unit from you. If those hold up, a flexible plan is a real advantage.
Quick answers
What does a 60/40 payment plan mean in Dubai?
You pay 60% of the purchase price in instalments while the property is under construction and the remaining 40% when it is handed over.
Do I pay the 4% Dubai Land Department fee at handover on an off-plan property?
No. On an off-plan purchase the 4% fee is paid when the sale contract is registered, near the start. There is no second 4% charge at handover.
Can I get a mortgage to cover the handover payment?
Often, yes, subject to bank approval. Lending on an unfinished property is capped at 50% of its value, and each bank has its own list of approved developers and projects.
SOURCES
- Khaleej Times: developers move to construction-linked payment plans (2026)
- Gulf News: buying off-plan in Dubai, fees, payment plans and checks
- Central Bank of the UAE rulebook: mortgage loan regulations
- The Kareem Ibrahim Investment Playbook, 2026 edition: supply and completion data (Property Monitor)
General information only, correct to the best of our knowledge in November 2026. It is not financial, tax or legal advice. Fees and rules change; confirm them before you act.